       With the last few dozen vehicles queuing to reach Yantai Port in Shandong, the first shipment of the Win Alliance Guinea project undertaken by Zigong Transport Machinery Group was successfully delivered, and Guinea was shipped.

The first batch of vehicles arriving at the port
 
       Sichuan Zigong Transport Machinery Group Co., Ltd. signed the port belt conveyor of the Win Alliance Guinea project in 2019 with a direct contract value of more than US $ 20 million. This is the largest single order in Zigong Yunji Group's export performance, and the company attaches great importance to it. The contract stipulates that the first batch delivery date is March 31, 2020.

Zigong transport aircraft ordered to prevent "epidemic" to resume production

       Because the project belongs to Africa, the technical requirements are high, the production process requirements are complex, the delivery time is tight, and the impact of the new coronary pneumonia epidemic that has swept the world makes the implementation of the project very difficult. After analyzing the many difficulties of the project, Yunji Group faced the difficulties and faced the difficulties and organized a large number of human and material resources to tackle the project. The technical and production problems were overcome one by one.

Overtime and overtime delivery

       However, the impact of the epidemic was unavoidable. When other enterprises were still shutting down for production, Yunji Group responded to the government's call and made a thorough arrangement for resumption of production. Resumption of work, where almost all local employees resume work. This laid a solid personnel base for the smooth delivery of the project. Through more than 40 days of overtime work, the first batch of goods was delivered according to the planned quality and quantity, which laid a solid foundation for the completion of the basic goals of the Yunji Group this year.